Large Battery Installation Opportunity
17th June 2020 – 2nd July 2020
A community energy group in Bridport requires a 500-kW/1,110-kWh battery.
Project:
Hazelmead Community Energy, who are installing a solar-powered microgrid in a new development in Bridport, would like to invite tenders to deliver a 500-kW/1,110-kWh battery.
Tender Timelines:
The tender timelines are set to ensure Hazelmead Community Energy can submit a revised grant application in early July.
- 17th June 2020 Tender Out
- 2nd July 2020 Tenders back
Installation Timeline:
Main Contractor decision / funding early July 2020
Installation: 4th Quarter 2020/1st Quarter 2021
Specification:
Technical details can be found here. The pricing spreadsheet referred to in the specification document can be found here.
Selection:
The selection of the successful contractor will be based on an objective assessment of the received quotes with 40% weight given to price, 20% to quality and experience and 40% to confidence/delivery.
Application:
If you would like to tender for the installation, then please contact Damon Rand by email at damon@cepro.co.uk. Further details will be provided on request.
If you are having any difficulty, please contact Derek Moss on derek.moss@dorsetcouncil.gov.uk